Major Petrochemical Company Eliminates Downtime Before Oil Upgrade
Client

Major Petrochemical Company

Location

Qatar

Read PDF Case Study

Major Petrochemical Company

Problem

A petrochemical company began preparing their compressors for an oil upgrade when they noticed deposits in their system. Upon further analysis, it was discovered that the MPC levels were above 50. These deposits could potentially contaminate the new oil being placed into the system and cause some unexpected downtime.

Solution

Fluitec’s partner, Ocean Team Qatar a Petrotec company, recommended Fluitec’s ESP (Electrophysical Separation Process) and a unit was placed on the reservoir of the compressor system and Boost VR+ was also added to aid in the removal of these deposits. This was done approximately 3 months prior to the scheduled oil change.

Results

  • MPC values were reduced to half within 4 days
  • MPC values were maintained under 10 during the 3 month period before the oil change
  • 2 months after the oil change, the MPC levels remain below 10
  • System is varnish free

$55,000 in Cost Savings 